Planning an office move around your IT

Plan internet, cabling, phones, backups and testing before an office move, including the Canadian emergency-calling details to check with your provider.

A man packing desk equipment into a cardboard box.

Staff can unpack their computers in an afternoon. Getting a new internet connection installed, cabling run and phone numbers ready may take much longer. Start the IT plan while you’re assessing the premises.

Choose one person in the business to coordinate decisions with the landlord, contractors, movers and service providers. Keep a shared schedule with an owner for each dependency and a date for testing it.

Check the premises before committing

Ask your IT provider to inspect the proposed space against a floor plan. Show them the desks, meeting rooms, reception, printers and any equipment that needs a wired connection.

Confirm cable routes, working network outlets, power and a secure, ventilated place for the firewall and switches. Ask building management who can carry out cabling work, when providers can enter, and whether approvals are needed for work in shared areas. Agree on cabling tests and labels before the contractor closes the work.

List the business activities the office must support. Include answering calls, taking payments, printing labels, scanning documents and accessing specialist applications. That list becomes your acceptance checklist.

Order and test internet early

Obtain availability and installation details for the exact unit. A provider serving the building may still need a survey, landlord approval or cabling to reach your space. Get the required work and expected activation date in writing.

Choose capacity around your cloud applications, calls, meetings and file transfers. Microsoft’s network assessment guidance recommends checking connectivity at each office. Test performance from the rooms where staff will work. A good result beside the router tells you little about a video call at the far end of the office.

If you’ll use cellular backup, test reception, data limits and firewall failover at the new address. Decide which activities can continue on it. Keep the old connection until the new service and your fallback are usable, subject to the lease and contract dates.

Confirm phone numbers and emergency calling

Ask the phone provider whether the move requires a number port, an address change or new equipment. Get a confirmed schedule before cancelling any service that holds a number you need to retain.

Canadian CRTC guidance on VoIP and 9-1-1 distinguishes fixed-location service from service that can be used in different locations. Ask your provider what applies to your setup, including staff using business calling apps away from the office.

Update the emergency-service location information the provider requires and confirm when it takes effect. The CRTC’s VoIP guidance explains why the registered address must stay current and why internet or power failures can interrupt calling. Keep an alternative way to call, such as a charged mobile phone, available during the move. Arrange any emergency-call testing through the provider; don’t make an unscheduled 9-1-1 test call.

Check alarms, entry systems, payment terminals, fax equipment and other services separately with their suppliers. Confirm what each needs at the new address. A phone jack on the wall doesn’t mean an older device designed for a copper line will work there.

Prepare equipment, access and backups

Decide what you’ll move, replace or retire. Record device identifiers and intended locations, label cables and power supplies, and agree who packs, transports and receives each item. Keep backup drives and security keys in tracked custody.

Have the technical team confirm backups and test a restore of critical data before disconnecting equipment. Save the network configuration and document how essential systems will be recovered. Cloud services still need a review of what data and settings your own backup covers.

Check whether the new public IP address affects vendor allowlists, remote access or connections between offices. Plan the changes with the relevant providers. Preserve guest-network separation and management access when configuring the new network.

Agree on a cutover and fallback

Write down when staff must stop using affected systems, which services come back first and who decides whether the new office is ready. Give staff a contact method that works while office email or phones are unavailable.

If the new connection or cabling isn’t ready, the fallback might be planned remote work or a delayed move for part of the team. Test the devices and access needed for that option in advance. Avoid putting unrelated upgrades into the same cutover unless they’re required for the move.

Test real work before staff arrive

Use the acceptance checklist from the planning visit. Test business applications, inbound and outbound calls, a video meeting, printing, scanning and payment systems. Check meeting rooms and reception as well as desks. Test remote support and backup connectivity too.

Record failures, owners and retest results. Arrange support for the first working day and ask staff to report missing or unreliable services. Update asset records, diagrams, monitoring, supplier addresses and public contact details once the move is confirmed.

Close out the old office

Walk through the old premises before handing back the keys. Account for computers, phones, storage devices, network equipment and paperwork with sensitive information.

For equipment being returned, sold or recycled, sanitize the storage first. The Cyber Centre’s disposal guidance explains that deleting files isn’t the same as sanitizing storage. Choose the method based on the device and the sensitivity of its data, and keep a record of the work.

Cancel old services only after the new setup is accepted and any number transfer is complete. Keep written cancellation confirmations and check the next invoices for charges that should have stopped.